Tuesday, September 2, 2025

Back to School

The first part of August saw the completion of the final module of benchwork and tying it into the layout.


Final_Module.jpg


Then it was on to connecting the Bakery tracks, which I have completed along with the industrial tracks in that area. I decided to go with Walthers Branchline Code 70 with wood ties. At $50 for 5, 36” pieces versus Micro Engineering Code 70 Nickel Silver Rail at $8 per 36” rail plus ties. That’s $80 plus ties for the same 15 feet of track. Cost and laziness won out.





I have three of the four curved turnouts connected to the slide switch mounts under the layout and rods through the fascia for control (The green knobs in the video above). The fourth one has been a bit of a pickle, as the throwbar sits atop a module joyce, so I have been trying to figure out a different way to connect the throwbar to the slide switch. I haven’t quite got it straight in my mind yet, but I think I will have to go back to Cs & Zs for this one. I’ll explain once I figure it out.


I installed the two left turnouts of the center runaround and connected them. Once I got to this point, procrastination set in, and one of my projects caught my attention. I’m also waiting on rail joiners, so Ozzy’s spur didn’t get laid, and no power connection.


As for the project, I bought one of these Treadmills off eBay, and I want to use it for speed matching my locomotives.


Treadmill_testing.jpg


I drilled a hole in one of the wheel bogey ilders and used an IR detector to count pulses. Now, using a little math, I have a speedometer.


Speedometer_Treadmill_Bogey.jpg


The foreground wheel on the left is the one with the hole. I have had an issue with erroneous pulses. I’m still working on that. An issue with traction as the locomotive doesn’t spin the wheel bogey ilder reliably. I found a product called “Bullfrog Snot”. It’s a liquid rubber product used for traction tires. It looks like it will work if I can get a thin enough layer on the idler.


I will be buying one box of track a month. I have my September box, so I should be
able to finish the center section and start on the right side, with the hope of having all
the track down by the end of October. I need to build three left-hand turnouts for the
center section, and have four quick strips printed. Once my order for rail joiners
comes in, I can complete the center section. In the meantime, Wiring is the name of
the game.


Until next month.


Victor

Saturday, August 2, 2025

Progress

Welcome to the warm days of summer. The month of July saw significant progress.

First, I built the 5-foot module I teased last month. Then, I moved the on module I had here to its proper location.
Next, I retrieved the other two modules that I had stored and hung them, and voila.

Overview.jpg


Here is a closer look from left to right.

Layour1.jpg

Layout2.jpg

Layout3.jpg

Layout4.jpg

layout5.jpg

Layout6.jpg

Layout7.jpg


The last photo shows where the final module will go. I have the parts, but I still need to build and mount it.


I haven’t seen it done before, so I guess it is unusual. As I had entered my track plan in AnyRail, I printed it at 1-1 scale and pasted it down with Mod
Podge. That accounts for the colours.


I completed the three left-hand curved turnouts and CADed up left and right sweepsticks and had them 3D printed.
Then the right-hand curved turnout was laid for the interchange tracks.

StagingTurnouts.jpg


You may have noticed the green knob in the lower right corner of the photo above. It is the control for the turnout. It is connected
to a side-mounted slide switch.

SidemountedSlidSwitch.jpg


The slide switch fits into a holder I designed and had 3D printed.

TurnoutControl.jpg


After that, I laid in the three key turnouts of the bakery.

KeyTurnouts.jpg


As can be seen in the photos, I have brought in some of the building flats from my old layout. Storage has bent them, but they give some
context as to size. They were made using a Cricut. I will detail that process when I start building the structures for the layout.

My next goal is to connect the interchange tracks to the bakery turnouts.

NextWork.jpg


Followed by laying the rest of the bakery track, start on the central runaround track, the Ozzy’s Pets spur, and hopefully get
power to the tracks..

I am undecided about hand-laying the track or using flex-track. I used flex-track on the interchange tracks and handlaid the connecting
rails using flex-track ties. Hand-laying lets me reuse rail from the old layout. At $10 CDN a stick for flex-track, it is something to consider,
though rail is not any better at $8 CDN a rail. Using that math flex is the way to go.


Until next Month.

Monday, August 17, 2020

Running around, Finally!

It has taken a couple of weeks but I now have the east end of the Sugarwood Siding connected.
IMG_2468.jpg

That in itself does not allow me to preform run a around because, the west turnout of Sugarwood Siding is at the end of the curve coming from the west. So that curve had to be laid and is complete now.

Spline roadbed laid and laying the ties.
IMG_2470.jpg

IMG_2471.jpg

IMG_2472.jpg

Rails down.
IMG_2473.jpg

IMG_2474.jpg

IMG_2475.jpg

With the exception of the spurs for McFoods and Olie’s Cold Storage the Sugarwood Yard section is complete.
SugarwoodYard-2.png

As can be seen in the pictures above I have started working on McFoods and I have mocked up the wall panels.
IMG_2469.jpg

I don’t think I will be installing the McFood and Olie’s Cold Storage spurs until I have the structures figured out. For now, the next step is run trains and push/pulls cars and get the track reliable. My Genset and MP15AC (B type trucks - 2 axles) have no issues with any portion of the track work so far but my SD40-2 (C type trucks - 3 axles) has an issue with the diverging route of the turnout at the east end of Surgarwood Siding.

I also want to get the other three modules of the layout built and install before the end of September.

Until next time.

For information about me check out the About page on this blog.

Tuesday, August 4, 2020

I’m about to run around!

Over the past week and holiday, I was able to complete laying the track for the Sugarwood Yard and I started laying the sub-roadbed to complete the east end of Sugarwood Siding.

There is not a whole lot to be said about laying the track in the yard it is pretty straight forward. Thought I did want the yard to look like it has been around for a while so I did not use a straight edge to lay the yard perfectly straight, as can be seen in the two photos below.

Theyard1.jpg

Theyard2.jpg

To connect the east end of Sugarwood Siding I decided to go with the spline roadbed approach and I find it easier and faster than I thought. I am using 1/8” x 1/8” basswood glued to the foam. I have been surprised that how fast the glue dries, about thirty minutes after laying a spline I can remove the pins and lay another spline. Towards the upper center of the top photo and left center of the bottom photo, the east end of Sugarwood siding can be seen.

Until next week.

For information about me check out the About page on this blog.

Monday, July 27, 2020

A Slow Week

Work on the layout proceeded a bit slower this week.

I having been working on Sugarwood Siding and had to build the two industry turnouts for McFoods and Olie’s Cold Storage. These two turnouts are now installed and connected to the west end of Sugarwood Siding.
sugarwoodsiding.jpg

I am stilling deciding on just how to connect the east end of the siding and the industry tracks.
eastonnection.jpg
McFoodsTurnout.jpg

My current thinking is to use 1/8-inch x 1/8-inch strips and take the spline roadbed approach. Another approach I am considering is to create a template and cut it out of a plank of basswood.
plankandtemplate.jpg

The benefit of the plank and template is that most of the work could be done at my workbench, the reason I am using 1/8-inch basswood/plywood for my roadbed, but I think there would be a lot of waste using the plank and template. I will have to think a bit more.

In the meantime, maybe I will work on the yard tracks.

Until next week.

For information about me check out the About page on this blog.